Upcoming works at our sites on Harvil Road and Newyears Green Lane

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-9-08/02/2021

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Harvil Road, Newyears Green Lane
Contractor
SCS JV
Type of works
Early construction works, Piling, Road closure
Estimated Start Date
02/08/2021
Estimated End Date
22/12/2021

What we are doing

Upcoming works
Works are ongoing at our sites at Harvil Road and Newyears Green Lane to build the new bridge over the Chiltern Line railway, the Copthall tunnel and the conveyor system.

From 2 August 2021, we will be carrying out the following activities:

• Piling works for the west portal of the Copthall tunnel
• Installation of the conveyor bridge over Newyears Green Lane
• Installation of support structures (abutments and wingwalls) for the new
bridge over the Chiltern Line railway
• Sheet piling at the MSD buildings off Breakspear Road South

We will continue to monitor noise, dust and vibration throughout our works and ensure that adequate measures are in place to minimise disruption.  Please see the following pages for more information about locations and the works we will be carrying out over the next few months.

Please see pdf attachment for more information about locations and the works we will be carrying out over the next few months.

1. Piling works for the Copthall tunnel
From 2 August to 18 September 2021, we will be carrying out piling work for the construction of the west portal of the Copthall tunnel.
The west portal pilling will be delivered using Continuous Flight Auger (CFA) techniques. CFA piling is when a continuous auger (hollow stem) is drilled into the ground to the required depth. Once the required depth is achieved, concrete is installed via the piling rig and through the hollow stem auger. The auger is then slowly withdrawn, and reinforced steel cages are installed. This method should not cause any disruption.

2. Road closure for conveyor bridge installation over Newyears Green Lane
From week commencing 2 August 2021, we will lift and install the conveyor bridge over Newyears Green Lane. A temporary road closure will be in place to ensure the installation can be carried out safely.
These works are dependent on weather conditions and we will therefore require two weeks after the start date as contingency to complete them. We anticipate the road closure to be in place for up to five days.  We will provide you updates at HS2inHillingdon.co.uk

3. Support structure installation
From 7 August 2021, we will be constructing the abutments and wingwalls, support structures for the new bridge over the Chiltern Line railway.
An abutment is a substructure unit located at the end of a bridge. Its function is to provide end support for the bridge superstructure. Wingwalls are also located at the ends of a bridge. Their function is to retain and provide support to the abutments.
For safety reasons, some of these works will take place between midnight and 6am, Saturday to Thursday, when trains are not running.

4. Sheet piling at MSD building

From 9 to 27 August 2021, we will be installing sheet piles at the MSD Building located off Breakspear Road South within our site.
Steel sheet piles will be installed in sequence along the planned perimeter and pressed into position. When arranged side by side, the sheet piles form a wall to provide earth support. We will not be expecting any disruption for these works.