Update: Notice of night works at West End Road
Work item: HS2-MW-SCS-Ph1-Ar-So-S2-UT-35-29/03/2021_2
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Ruislip
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 26/04/2021
- Estimated End Date
- 05/05/2021
What we are doing
What we are doing
We wrote to you previously to advise you that we would be carrying out utility surveys from 13 to 16 April 2021. However, we have rearranged these dates and the surveys will now take place from 26 April to 5 May 2021.
We will be carrying out sewer system investigations along West End Road, in the area shown on the map overleaf. This will help to inform our design decisions in the area.
We will investigate the condition of the sewer system using a CCTV camera mounted on a small robot. We may need to flush the drainage system using a high-pressure water jet should we find a blockage in order to carry out the investigation.
How the surveys might affect you
The surveys will be carried out below street level, therefore temporary traffic management will be in place to ensure the surveys can be carried out safely.
Your utility services will not be affected.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]